ProcessPLUS® Acceptance Test
ProcessPLUS® Acceptance Test –
independent with high-precision


APPROACH
  1. BTB Jansky generates a plant model and maps plant process conditions before and after retrofit.
  2. ProcessPLUS® Acceptance Test is performed remotely at BTB Jansky offices. Process data is analyzed off site.
  3. Process modeling is usually done 3-4 weeks prior to retrofit. After receiving the pre-retrofit process data the reconciliation of data is performed and results are presented.
  4. The final results of the delta analysis in the course of a ProcessPLUS® Acceptance Test are available after receiving the post-retrofit process data. One week later, the official acceptance test report is delivered.